Questar Pipeline Company
Summary of Short-Term AvailabLe Capacity
Revised  June 26 , 2008

 

Firm T-1

From

To

Minimum Acceptable Rates

Delivery Capacity (Dth/d)

Receipt Points 1

Delivery Points 1

Monthly Reservation
Charge Per Dth 2

Equivalent Rate per Dth
at 100 % Load Factor 2

0

System-wide receipts

TransColorado

Max Rate

$.17652

3,000

Northern system various Overthrust area points

Questar Gas Wasatch Front

Max Rate

$.17652

16,870

Northern system points

Northwest at Crossover 16

Max Rate

$.17652

60,670

QPC on Overthrust

Kern River at Roberson Creek

Max Rate

$.17652

16,360

Capacity to Overthrust thru Eakin

Kern River at Roberson

 

 

44,000

Northern system East of Kanda

WIC, CIG or QOPC

Max Rate

$.17652

58,530

Northern system points West of Kanda

WIC, CIG or QOPC

Max Rate

$.17652

4,000

Southern system various points

CIG at Natural Buttes

Max Rate

$.17652

0

Northern system points

Williams at Skull Creek

Max Rate

$.17652

0

Fidlar

Clay Basin on ML 80

Max Rate

$.17652

0

Oak Spring

Payson on ML 41

Max Rate

$.17652

27,400

Northern system West of Map #318

Map 318  General Chemical

$1.43962

$.05000

0

Northern system East of Map #318

Map 318 General Chemical

$2.35212

$.08000

27,400

Northern system West of Map #307

Map 307-General Chem #6

$1.43962

$.05000

0

Northern system East of Map #307

Map 307-General Chem #6

$2.35212

$.08000

Receipt and delivery points not listed above.

Max Rate

$.17652

Questar Pipeline Company's maximum Monthly Reservation Charge is $5.28804 per Dth.

Questar may agree, through acceptance in its contracting system, to allow a variety of discounts between its maximum and minimum rates under any rate schedule in its tariff without undue discrimination. Such discounts may be in addition to a base discount and will not be considered a material deviation from Questar's forms of service agreements when Questar and Shipper agree that a discount applies.

Monthly unsold capacity reports are posted on the Unsubscribed capacity section of the Questar Pipeline website.  The reports include the following:

The Map of short term unsold report is a flow diagram showing unsold firm capacity.

The Short-term unsold  -- map point listing report shows all system-wide available short term capacity at all receipt and delivery points.  The report allows shippers to query the system to determine available capacity at specific receipt and delivery points.

______________________________________________

(1) Refer to the Short term unsold -- map point listing report for capacity at specific receipt and delivery points.

(2) The Short term unsold - map point listing report indicates what receipt and delivery points require the use of third party facilities (OT*-Questar Overthrust Pipeline).  Shipper shall be responsible for paying any third party transportation or processing costs in addition to Questar Pipeline's maximum T-1 transportation rate.  Shipper's bid must include any reservation fees associated with these third party fees.  If the total reservation fee exceeds Questar's maximum reservation rate, then Shipper's bid must also include language that reflects they are willing to pay a negotiated rate.  Contact your marketing representative to establish any additional charges that would be necessary.

The current incremental monthly reservation charge for capacity that requires Questar Overthrust Pipeline Company backhaul is $1.06458 per Dth.  Contractual agreements that incur the additional backhaul charge above the maximum rate will be filed with the Federal Energy Regulatory Commission with a negotiated rate prior to gas flowing.

Top